2025/26 Local Growth Fund (LGF): Proposed Spend Profile

*Figures provided below relate only to LGF investment and do not include other scheme contributions 

Scheme  

Total LGF Allocation (£) 

LGF Spend to 31/03/25 (£) 

25/26 LGF Profile (£) 

Future Years spend (26 LGF Spend in future years (£)

Hailsham/Polegate/Eastbourne movement and access transport scheme 

2,100,000.00

2,042,371.22

57,628.78

-

Eastbourne and South Wealden walking and cycling LSTF package 

6,600,000.00

4,751,549.72

1,848,450.14

-

Hastings and Bexhill movement and access package 

9,000,000.00

5,159,131.46

2,076,000.00

1,764,868.54

Eastbourne town centre LSTF access and improvement package 

8,000,000.00

6,332,346.34

1,667,653.66

-

Total

25,700,000.00

18,285,398.74

5,649,732.58

1,764,868.54